Construction Updates

Obsidian Construction Update - February 2026

Ground floor fit-out complete. Internal fit out underway up to level 10. Show apartments underway.

Obsidian Construction Update - September 2025

Level 13 fully cast. Windows installed level 13. Brick façade fitting commenced.

Obsidian Construction Update - March 2025

Foundations and site preparation. Level 1 slab underway. Second core commenced.

Obsidian Construction Update - January 2025

Foundations complete. Street utility installation complete. Core top out. 

Obsidian Construction Update - November 2024

Foundations complete. Street utility installation. Core topping out. 

Obsidian Construction Update - October 2024

Foundations complete. Core topped out. Preparation for slabs.

Obsidian Construction Update - August 2024

Foundations complete. Slip core at Level 3. Sample façade complete.

Obsidian Construction Update - July 2024

Foundations complete. Preparing site for concrete slip pore. Preparing site for crane erection.

Obsidian Construction Update - June 2024

Foundations for core complete. Stand for crane in place. Branded hoardings erected. 

Obsidian Construction Update - May 2024

Site fully mobilised with hoardings erected. Groundworks commenced. Piling and foundation work underway.

Obsidian - Development Walkthrough

Obsidian, which has just started construction, is a premium and luxury development in the heart of Manchester city centre.Â